ISA/IEC 62443-3-2:2020, Clause 4.5 covers risk comparison as zone and conduit requirement ZCR 4.
ZCR 4 is the decision gate between the initial assessment and deeper work. Compare the initial risk from ZCR 2 with the organisation’s tolerable risk. If initial risk already sits within that tolerance, detailed assessment may not be required; if it exceeds tolerance, ZCR 5 becomes mandatory.
Reference: ISA/IEC 62443-3-2:2020, Clause 4.5
Related:
Zone, Conduit and Risk Assessment (Clause 4)
|
ZCR 2 – Initial Risk Assessment
|
ZCR 5 – Detailed Risk Assessment
ZCR pages: ZCR 1 | ZCR 2 | ZCR 3 | ZCR 4 | ZCR 5 | ZCR 6 | ZCR 7
Reference: ISA/IEC 62443-3-2, Clause 4.5
Clause: 4.5.2
Tolerable risk is an organisational policy choice, typically expressed through the same risk matrices or criteria used elsewhere in the business. ZCR 4 does not invent a new scale; it forces an explicit yes/no on whether the design effort moves into per-zone detailed analysis.